The process of window installation in the majority of Bory Promenáda phase is almost finished

Window installation in the third stage of Bory Bývanie project is slowly coming to an end. There are two remaining houses left to be completed. So far, they have windows installed up to the second floor. 

At the same time, we are equally committed to be working on adding gravel to the individual roofs as well as installing heating and electrical systems. 

There is still an important step to be done which is to connect water and gas to the public supply network.